PDO firms up plans for two wind farm projects in Oman

by Ahmed Alsir
September 5, 2023
in Companies, Local News
0
PDO firms up plans for two wind farm projects in Oman
0
SHARES
39
VIEWS
Share on FacebookShare on Twitter

MUSCAT: Building on its pioneering and broad-based renewable energy development strategy, Petroleum Development Oman (PDO0, the biggest oil and gas producer in the Sultanate of Oman, has progressed plans for the development of a pair of wind power projects to support its transition into a low-carbon energy company.

Also making headway is a separate initiative centring on the development of a utility-scale solar PV based Independent Power Project (IPP), integrated with a first-ever battery energy storage system (BESS), at Qarn Alam in its Block 6 concession.

Majority state-owned PDO said in a new report on Wednesday that a Request for Proposals (RfP) for two wind power projects, each of about 100 MW capacity, will be floated this year.

Plans for the two wind farms, dubbed ‘Riyah-1 and Riyah-2, were green-lighted following the completion of a feasibility study and site measurement campaign that had concluded that PDO’s concession had “excellent wind potential with an average speed of 8 metres/second”.

While Riyah-1 is targeted for completion by Q2 2026, Riyah-2 is expected to be ready by Q4 2026. Their operationalization will help PDO meet its goal of securing around 30 per cent of its energy needs from renewable sources by 2026.

Plans for a new solar PV based IPP of around 100 MW capacity are also being firmed up for development over the next couple of years. Dubbed the ‘North Solar Storage IPP, the proposed project will be broadly modelled on PDO’s landmark 100 MW Amin Solar PV IPP, which came into operation in the south of the company’s concession in May 2020. It was PDO’s – as well as Oman’s – first utility-scale solar PV project.

Read more

This time around, PDO’s North Solar Storage IPP at Qarn Alam near Saih Nihayda will include – also for the first time in Oman – a battery energy storage system (BESS), sized to supply and store electrical energy and deliver a maximum 100-MW peak power into the company’s grid during daylight hours. This stored energy will be fed back into the grid continuously until daybreak the following day.

“This system will use a PV single-axis tracking battery energy storage based on lithium-Ion battery technology. This daily cycle will then be repeated for each day of the year throughout the project’s term. The developer will be encouraged to optimise the design of the plant and offer the lowest tariffs for the delivery of electrical energy at the delivery point,” the company explained, adding that the project is slated to come on stream in 2025.

Significantly, the Amin Solar IPP located near Nimr is also the world’s first utility-scale solar project to have an oil and gas company as the sole buyer of electricity. As of end-2022, it had generated more than 800,000 MWh of renewable energy, helping substitute supply from gas-based generation and thereby reducing greenhouse gas (GHG) emissions as well.

Further, as part of its broader decarbonisation strategy, PDO is set to commission solar ground-mounted systems at three of its internal airports at Marmul, Qarn Alam and Fahud this year. “The project is a first of its kind and will produce and channel green electricity to cover the airports’ electrical load during the daytime. It will boast a total installed capacity of 609 kW,” the company stated.

Also continuing apace are initiatives to expand its solar car park capacity at the Mina Al Fahal headquarters, commission solar rooftop systems at other PDO-owned buildings and infrastructure.

SOURCE: OMAN DAILY OBSERVER

DATE: 31 Aug 2023

Tags: omanPDOWind Power
Previous Post

Oman weighs second interconnect to boost power trades with GCC

Next Post

PDO oil production targeted at 659,000 bpd in 2023

Ahmed Alsir

Ahmed Alsir

Related Posts

PDO boosts In-Country Value with $2.5bn investment
Companies

PDO boosts In-Country Value with $2.5bn investment

May 28, 2024
Oman, Netherlands explore cooperation in hydrogen ports
Companies

Oman, Netherlands explore cooperation in hydrogen ports

May 28, 2024
Oman takes part in Rotterdam Hydrogen Summit
Companies

Oman takes part in Rotterdam Hydrogen Summit

May 28, 2024
Oman launches strategic study on energy mix, storage options
Companies

Oman launches strategic study on energy mix, storage options

May 28, 2024
Next Post
PDO oil production targeted at 659,000 bpd in 2023

PDO oil production targeted at 659,000 bpd in 2023

About

Oman’s single news and information resource and discussion platform for the dynamic energy sector.

Category

Local News
Green Hydrogen
Regional News
Carbon Capture
International News
Energy Cooperation
Companies
Energy Storage

Quick Links

Home
Publications
Advertise
Archive
Research Papers
Interviews
CCUS Forum
About Us
GHSO
Contact Us
info@energyoman.net
+968 29855714

© 2023 Energy Oman Magazine All Rights Reserved

No Result
View All Result
  • Home
  • About Us
  • EOSI
  • Events
    • GHSO 2023
    • CCUS Forum 2023
  • Archive
  • Media
    • Interviews
    • Press Releases
    • Publications
  • Advertise
  • Contact Us

© 2023 Energy Oman Magazine - Oman's single news and information resource and discussion platform for the dynamic energy sector.